WL26-005
Ready to scheduleBiological seed dressing · Lachlan Biologicals
- QuoteSat, 22 Aug
- ApprovedSat, 5 Sept
- Scheduled—
- Started—
- Field done—
- Report—
- Completed—
- Closed—
Plan v1 · Original plan · 19 Sept 2026 by Tom Brennan
Week of
28 Sept5 Oct12 Oct19 Oct26 Oct2 Nov9 Nov16 Nov23 Nov30 Nov7 Dec14 Dec21 Dec
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
| Date | Task | Calculated from | Window | Who | Status |
|---|---|---|---|---|---|
| Mon, 28 Sept | Chemical on hand | 14 days before Application 1 | on the day | Tom Brennan | planned |
| Mon, 5 Oct | Site ready | 7 days before Application 1 | on the day | Tom Brennan | planned |
| Mon, 12 Oct | Application 1 | Fixed date | on the day | Liam O'Connor | planned |
| Mon, 12 Oct | 0 DAT assessment (Application 1) | 0 DAT from Application 1 | on the day | Liam O'Connor | planned |
| Mon, 26 Oct | 14 DAT assessment (Application 1) | 14 DAT from Application 1 | until Tue, 27 Oct | Liam O'Connor | planned |
| Mon, 9 Nov | 28 DAT assessment (Application 1) | 28 DAT from Application 1 | until Tue, 10 Nov | Liam O'Connor | planned |
| Mon, 23 Nov | 42 DAT assessment (Application 1) | 42 DAT from Application 1 | until Tue, 24 Nov | Liam O'Connor | planned |
| Mon, 23 Nov | Field work complete | Same day as 42 DAT assessment (Application 1) | on the day | Tom Brennan | planned |
| Mon, 14 Dec | Report draft due | 21 days after Field work complete | on the day | Tom Brennan | planned |
| Mon, 21 Dec | Report approved | 7 days after Report draft due | on the day | Helen Marsh | planned |