WL26-006
ScheduledInsecticide seed treatment · Canobolas Crop Protection
- QuoteFri, 14 Aug
- ApprovedFri, 28 Aug
- ScheduledFri, 18 Sept
- Started—
- Field done—
- Report—
- Completed—
- Closed—
Plan v1 · Original plan · 18 Sept 2026 by Priya Raman
Week of
14 Sept21 Sept28 Sept5 Oct12 Oct19 Oct26 Oct2 Nov9 Nov16 Nov
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
| Date | Task | Calculated from | Window | Who | Status |
|---|---|---|---|---|---|
| Wed, 16 Sept | Chemical on hand | Completed (date locked) | on the day | Priya Raman | completed |
| Wed, 23 Sept | Site ready | Completed (date locked) | on the day | Priya Raman | completed |
| Wed, 30 Sept | Application 1 | Fixed date | on the day | Jess Walker | planned |
| Wed, 30 Sept | 0 DAT assessment (Application 1) | 0 DAT from Application 1 | on the day | Jess Walker | planned |
| Sat, 3 Oct | 3 DAT assessment (Application 1) | 3 DAT from Application 1 | until Sun, 4 Oct | Jess Walker | planned |
| Wed, 7 Oct | 7 DAT assessment (Application 1) | 7 DAT from Application 1 | until Thu, 8 Oct | Jess Walker | planned |
| Wed, 14 Oct | 14 DAT assessment (Application 1) | 14 DAT from Application 1 | until Thu, 15 Oct | Jess Walker | planned |
| Wed, 21 Oct | 21 DAT assessment (Application 1) | 21 DAT from Application 1 | until Thu, 22 Oct | Jess Walker | planned |
| Wed, 21 Oct | Field work complete | Same day as 21 DAT assessment (Application 1) | on the day | Priya Raman | planned |
| Wed, 11 Nov | Report draft due | 21 days after Field work complete | on the day | Priya Raman | planned |
| Wed, 18 Nov | Report approved | 7 days after Report draft due | on the day | Helen Marsh | planned |