All trials

WL26-006

Scheduled

Insecticide seed treatment · Canobolas Crop Protection

  1. Quote
    Fri, 14 Aug
  2. Approved
    Fri, 28 Aug
  3. Scheduled
    Fri, 18 Sept
  4. Started
  5. Field done
  6. Report
  7. Completed
  8. Closed

Plan v1 · Original plan · 18 Sept 2026 by Priya Raman

Week of
14 Sept21 Sept28 Sept5 Oct12 Oct19 Oct26 Oct2 Nov9 Nov16 Nov
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
DateTaskCalculated fromWindowWhoStatus
Wed, 16 SeptChemical on handCompleted (date locked)on the dayPriya Ramancompleted
Wed, 23 SeptSite readyCompleted (date locked)on the dayPriya Ramancompleted
Wed, 30 SeptApplication 1Fixed dateon the dayJess Walkerplanned
Wed, 30 Sept0 DAT assessment (Application 1)0 DAT from Application 1on the dayJess Walkerplanned
Sat, 3 Oct3 DAT assessment (Application 1)3 DAT from Application 1until Sun, 4 OctJess Walkerplanned
Wed, 7 Oct7 DAT assessment (Application 1)7 DAT from Application 1until Thu, 8 OctJess Walkerplanned
Wed, 14 Oct14 DAT assessment (Application 1)14 DAT from Application 1until Thu, 15 OctJess Walkerplanned
Wed, 21 Oct21 DAT assessment (Application 1)21 DAT from Application 1until Thu, 22 OctJess Walkerplanned
Wed, 21 OctField work completeSame day as 21 DAT assessment (Application 1)on the dayPriya Ramanplanned
Wed, 11 NovReport draft due21 days after Field work completeon the dayPriya Ramanplanned
Wed, 18 NovReport approved7 days after Report draft dueon the dayHelen Marshplanned