Report to be written

Crown rot rotation study · Ridgeline Crop Sciences

Report overdue — client needs it for registration dossier — owner: Priya Raman

Urgent1 overduePayment overdue
  1. Quote
    Tue, 9 June
  2. Approved
    Tue, 23 June
  3. Scheduled
    Tue, 14 July
  4. Started
    Tue, 21 July
  5. Field done
    Tue, 1 Sept
  6. Report
  7. Completed
  8. Closed

Plan v1 · Original plan · 2 Sept 2026 by Priya Raman

Week of
6 July13 July20 July27 July3 Aug10 Aug17 Aug24 Aug31 Aug7 Sept14 Sept21 Sept28 Sept
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
DateTaskCalculated fromWindowWhoStatus
Tue, 7 JulyChemical on handCompleted (date locked)on the dayPriya Ramancompleted
Tue, 14 JulySite readyCompleted (date locked)on the dayPriya Ramancompleted
Tue, 21 JulyApplication 1Completed (date locked)on the dayLiam O'Connorcompleted
Tue, 4 AugApplication 2Completed (date locked)on the dayLiam O'Connorcompleted
Tue, 4 Aug0 DAT assessment (Application 2)Completed (date locked)on the daySam Nguyencompleted
Tue, 11 Aug7 DAT assessment (Application 2)Completed (date locked)until Wed, 12 AugSam Nguyencompleted
Tue, 18 Aug14 DAT assessment (Application 2)Completed (date locked)until Wed, 19 AugSam Nguyencompleted
Tue, 1 Sept28 DAT assessment (Application 2)Completed (date locked)until Wed, 2 SeptSam Nguyencompleted
Tue, 1 SeptField work completeCompleted (date locked)on the dayPriya Ramancompleted
Tue, 22 SeptReport draft due21 days after Field work completeon the dayPriya RamanOverdue
Tue, 29 SeptReport approved7 days after Report draft dueon the dayHelen Marshplanned