WL26-013
Report awaiting approvalBiostimulant yield response · Lachlan Biologicals
Invoice ≠ quote
- QuoteFri, 19 June
- ApprovedFri, 3 July
- ScheduledFri, 24 July
- StartedFri, 31 July
- Field doneFri, 28 Aug
- ReportFri, 18 Sept
- Completed—
- Closed—
Plan v1 · Original plan · 18 Sept 2026 by Tom Brennan
Week of
20 July27 July3 Aug10 Aug17 Aug24 Aug31 Aug7 Sept14 Sept21 Sept28 Sept5 Oct
Preparation
Applications
Assessments
Reporting
ApplicationAssessmentReport / reviewDoneRescheduledOverdueMissedStaff clashToday
| Date | Task | Calculated from | Window | Who | Status |
|---|---|---|---|---|---|
| Fri, 17 July | Chemical on hand | Completed (date locked) | on the day | Tom Brennan | completed |
| Fri, 24 July | Site ready | Completed (date locked) | on the day | Tom Brennan | completed |
| Fri, 31 July | Application 1 | Completed (date locked) | on the day | Liam O'Connor | completed |
| Fri, 31 July | 0 DAT assessment (Application 1) | Completed (date locked) | on the day | Liam O'Connor | completed |
| Fri, 7 Aug | 7 DAT assessment (Application 1) | Completed (date locked) | until Sat, 8 Aug | Liam O'Connor | completed |
| Fri, 14 Aug | 14 DAT assessment (Application 1) | Completed (date locked) | until Sat, 15 Aug | Liam O'Connor | completed |
| Fri, 14 Aug | Application 2 | Completed (date locked) | on the day | Liam O'Connor | completed |
| Fri, 28 Aug | 28 DAT assessment (Application 1) | Completed (date locked) | until Sat, 29 Aug | Liam O'Connor | completed |
| Fri, 28 Aug | Field work complete | Completed (date locked) | on the day | Tom Brennan | completed |
| Fri, 18 Sept | Report draft due | Completed (date locked) | on the day | Tom Brennan | completed |
| Fri, 2 Oct | Report approved | 14 days after Report draft due | on the day | Helen Marsh | planned |